Knowledgebase

YZT - Defrost Board Replacement

Article ID: 719
Last updated: 30 Mar, 2023

York Heat Pump: YZT

Re: Defrost Board Replacement

When replacing a Communicating Defrost Board, it is required to manually set the unit tonnage before initial operation.

Set the unit tonnage by adjusting the dip switches as shown in the table below.

Switch 1 2 3 4 5
Factory  Off   Off   Off   Off   Off 
2Ton Off Off Off On Off
3Ton Off Off Off On On
4Ton Off Off On Off Off
5Ton Off Off On Off On

After the dip switches are set, press the PUSH BUTTON, greater than six seconds without a call for compressor operation. The new tonnage will be displayed on the 7-Segment display and the configuration will be stored in the controls the memory.

If the proper tonnage is not displayed, check and confirm dip switch selections, then repeat the above PUSH BUTTON operation once again.

It is not necessary to cycle power after configuring the tonnage.

This article was:   Helpful | Not helpful
Report an issue
Article ID: 719
Last updated: 30 Mar, 2023
Revision: 3
Access: Public
Views: 32
Comments: 0