Honeywell Thermostat: TH4110U T4 Pro
Re: Installer Setup Options
To enter Installer Setup:
- Press and hold the "Center" button and the "+" button together for 3 seconds.
- Press "Select" to enter Setup.
- Press "Select" to cycle through setup options.
- Press "+" or "-" to change values.
- Press "Select" to confirm changes or "Back" to ignore changes.
- To Finish and Save changes, press "Home".
Setup# |
Function |
Options |
120 |
Schedule Options |
- 0 = Non-Programmable
- 2 = 5/2 Programmable
- 3 = 5/1/1 Programmable
- 4 = 7 Day Programmable
|
125 |
Temperature Scale |
- 0 = Farenheit
- 1 = Celsius
|
200 |
Heat Equipment
|
- 1 = Conventional
- 2 = Heat Pump
- 3 = Radiant Heat
- 5 = None (Cool Only)
|
205 |
Heat Type |
- 1 = Standard Eff Gas
- 2 = High Eff Gas
- 3 = Oil Furnace
- 4 = Electric Furnace
- 7 = Air to Air Heat Pump
- 8 = Geothermal Heat Pump
- 9 = Hot Water Radiant
- 12 = Steam
|
218 |
Reversing Valve |
- 0 = O/B Energizes in Cool
- 1 = O/B Energizes in Heat
|
220 |
Cool Stages |
|
221 |
Heat/Backup Stages |
|
230 |
Heat Fan Control |
- 1 = Equipment Controls Fan
- 2 = Thermostat Controls Fan
|
300 |
System Changeover |
|
303 |
Auto Changeover Differential |
|
365 |
Cool 1 Cycle Rate |
|
370 |
Heat 1 Cycle Rate |
|
370 |
Aux Ht Cycle Rate |
|
387 |
Short-Cycle Time |
|
425 |
Intelligent Recovery |
|
430 |
Min Cool Setpt |
|
431 |
Max Heat Setpt |
|
435 |
Keypad Lockout |
- 0 = None
- 1 = Partial
- 2 = Full
|
702 |
Air Filter Qty |
|
711 |
Filter 1 Timer |
- 0 = Off
- 1 = 10 Run Days
- 2 = 20 Run Days
- 3 = 30 Run Days
- 4 = 45 Run Days
- 5 = 60 Run Days
- 6 = 90 Run Days
- 7 = 120 Run Days
- 8 = 150 Run Days
- 9 = 30 Calendar Days
- 10 = 45 Calendar Days
- 11 = 60 Calendar Days
- 12 = 75 Calendar Days
- 13 = 3 Calendar Months
- 14 = 4 Calendar Months
- 15 = 5 Calendar Months
- 16 = 6 Calendar Months
- 17 = 9 Calendar Months
- 18 = 12 Calendar Months
- 19 = 15 Calendar Months
|
712 |
Filter 2 Timer |
- 0 = Off
- 1 = 10 Run Days
- 2 = 20 Run Days
- 3 = 30 Run Days
- 4 = 45 Run Days
- 5 = 60 Run Days
- 6 = 90 Run Days
- 7 = 120 Run Days
- 8 = 150 Run Days
- 9 = 30 Calendar Days
- 10 = 45 Calendar Days
- 11 = 60 Calendar Days
- 12 = 75 Calendar Days
- 13 = 3 Calendar Months
- 14 = 4 Calendar Months
- 15 = 5 Calendar Months
- 16 = 6 Calendar Months
- 17 = 9 Calendar Months
- 18 = 12 Calendar Months
- 19 = 15 Calendar Months
|
1400 |
Backlight |
- 0 = On Demand
- 1 = Continuous
|
1401 |
Brightness |
|
1410 |
Clock |
|
1415 |
Daylight Savings |
|
1420 |
Temperature Offset |
|